two workers can finish building a play set in 18 hours how long will it take 4 workers to build 3 play sets
Logo

Nursing Elites

HESI A2

HESI A2 Math

1. If two workers can finish building a play set in 18 hours, how long will it take 4 workers to build 3 play sets?

Correct answer: A

Rationale: If 2 workers can complete building one play set in 18 hours, it means one worker would take 36 hours to complete the same task. When the number of workers is doubled to 4, the time is halved, so 4 workers would take 18 hours to build one play set. To build 3 play sets, the total time needed would be 3 times the time for one play set, which equals 54 hours. Therefore, 4 workers can build 3 play sets in 27 hours, making choice A the correct answer. Choices B, C, and D are incorrect because they do not account for the correct relationship between the number of workers and the time required to complete the task.

2. What is the result of multiplying 226 by 55.3?

Correct answer: B

Rationale: The correct answer is 12,541.8. To find this result, you multiply 226 by 55.3, which equals 12,541.8. Choices A, C, and D are incorrect because they do not reflect the accurate multiplication of 226 by 55.3.

3. Donald earns 8% of the selling price of each house he sells. If he sells a house for $152,000, how much does he earn?

Correct answer: B

Rationale: To calculate how much Donald earns from selling a house for $152,000 at an 8% commission rate, we multiply the selling price by the commission rate: $152,000 x 0.08 = $12,160. Therefore, he earns $12,160. Choice A, $12,160, is the correct answer as calculated. Choices C and D are incorrect amounts as they do not result from the given information. Choice C, $19,000, is significantly higher than the correct calculation, and choice D, $21,600, is the result of incorrectly adding the commission to the selling price instead of calculating the commission earned.

4. Tamison bought 20 stamps for 29¢ each and 40 stamps for 42¢ each. If she gave the postal worker $25, how much change did she receive?

Correct answer: A

Rationale: First, calculate the total cost of the 20 stamps bought at 29¢ each: 20 stamps * 29¢ = $5.80. Next, calculate the total cost of the 40 stamps bought at 42¢ each: 40 stamps * 42¢ = $16.80. The total cost of all stamps is $5.80 + $16.80 = $22.60. If Tamison gave $25 to the postal worker, her change is $25 - $22.60 = $2.40. Therefore, the correct answer is A. Option B, C, and D are incorrect as they do not reflect the correct change Tamison received after buying the stamps.

5. What is the numerical value of the Roman numeral XVII?

Correct answer: B

Rationale: The Roman numeral XVII represents the number 17. In Roman numerals, X stands for 10 and V stands for 5. When V (5) is subtracted from X (10), it results in 5 being subtracted from 10, which equals 5. Adding this to V (5) gives the total value of XVII as 17. Choice A is incorrect because it is not the correct numerical value of XVII. Choice C and D are also incorrect as they do not correspond to the Roman numeral XVII.

Similar Questions

What is 35% of 70?
What is the result of adding 1/2 + 4/5?
Your supervisor instructs you to purchase 240 pens and 6 staplers for the nurse's station. Pens are purchased in sets of 6 for $2.35 per pack. Staplers are sold in sets of 2 for $12.95 each. How much will purchasing these products cost?
A truck driver traveled 925 miles from 8 am Tuesday to 5 pm Wednesday. During that time, he stopped for 30 minutes for lunch and gas at 1 pm Tuesday. He stopped for the night at 7 pm and was back on the road at 5 am. What was his average speed?
Stewart has 56 acres of land. He wants to divide the land into plots of 0.25 acres. How many plots of land will Stewart have after he divides the 56 acres?

Access More Features

HESI A2 Basic
$99/ 30 days

  • 3,000 Questions with answers
  • 30 days access

HESI A2 Premium
$149.99/ 90 days

  • Actual HESI A2 Questions
  • 3,000 questions with answers
  • 90 days access

Other Courses