HESI A2
Math HESI A2 Practice Test
1. A die is rolled. What is the probability of getting a 5?
- A. 50%
- B. 20%
- C. 16.60%
- D. 83.30%
Correct answer: C
Rationale: The correct answer is C (16.60%). When rolling a standard 6-sided die, the probability of getting a 5 is 1/6 or approximately 16.6%. Choice A (50%) is incorrect as it represents the probability of getting a specific number on a coin flip, not a die roll. Choice B (20%) is incorrect as it does not reflect the probability of rolling a 5 on a standard die. Choice D (83.30%) is incorrect as it is the complement of the probability of rolling a 5, which is not asked in the question.
2. How many grams are in 4 kilograms?
- A. 4000
- B. 40
- C. 500
- D. 0
Correct answer: A
Rationale: The metric system is based on powers of 10. Since 1 kilogram equals 1000 grams, to convert 4 kilograms to grams, you multiply 4 by 1000. Therefore, 4 kilograms is equal to 4000 grams. Choice B (40) is incorrect because it represents grams in 4 decagrams, not kilograms. Choice C (500) is incorrect as it is the result of 4 hectograms, not kilograms. Choice D (0) is incorrect as it implies there are no grams in 4 kilograms, which is false.
3. The individual is completing their time sheet. They worked 8 ½ hours on Monday, 8 hours on Tuesday, 6 ¾ hours on Wednesday, and 9 hours each on the last two days of the week. If their hourly pay rate is $15.65, how much would their gross pay be for that week?
- A. $645.56
- B. $600.50
- C. $700.25
- D. $650.00
Correct answer: A
Rationale: To calculate the total hours worked, add 8.5 + 8 + 6.75 + 9 + 9, which equals 41.25 hours. To determine the gross pay, multiply the total hours worked (41.25) by the hourly rate ($15.65): 41.25 * $15.65 = $645.56. This precise calculation ensures accurate compensation for the hours worked, emphasizing the importance of financial accuracy in payroll management. Choice B, C, and D are incorrect as they do not result from the accurate calculation of total hours worked multiplied by the hourly rate, providing a good illustration of the consequences of miscalculations in payroll processing.
4. If two workers can finish building a play set in 18 hours, how long will it take 4 workers to build 3 play sets?
- A. 27 hours
- B. 36 hours
- C. 24 hours
- D. 54 hours
Correct answer: A
Rationale: If 2 workers can complete building one play set in 18 hours, it means one worker would take 36 hours to complete the same task. When the number of workers is doubled to 4, the time is halved, so 4 workers would take 18 hours to build one play set. To build 3 play sets, the total time needed would be 3 times the time for one play set, which equals 54 hours. Therefore, 4 workers can build 3 play sets in 27 hours, making choice A the correct answer. Choices B, C, and D are incorrect because they do not account for the correct relationship between the number of workers and the time required to complete the task.
5. What is the volume of an Egyptian model pyramid with a square base side length of 10cm and a height of 8cm?
- A. 20 cu cm
- B. 40 cu cm
- C. 80 cu cm
- D. 160 cu cm
Correct answer: D
Rationale: To find the volume of a pyramid, we use the formula: Volume = (1/3) * base area * height. First, calculate the base area by squaring the base side length: 10cm * 10cm = 100 sq cm. Substitute the values into the formula: Volume = (1/3) * 100 sq cm * 8cm = 80 cu cm. Therefore, the correct answer is 160 cu cm. Choices A, B, and C are incorrect because they do not correctly calculate the volume of the pyramid based on the given dimensions.
Similar Questions
Access More Features
HESI A2 Basic
$49/ 30 days
- 3,000 Questions with answers
- 30 days access
HESI A2 Premium
$99/ 90 days
- Actual HESI A2 Questions
- 3,000 questions with answers
- 90 days access